              OPTIMIZATION              
----------------------------------------
max maxLinkLoad	#tunnels	time (ms)
----------------------------------------
1164		1		103
1159		2		118
1135		3		130
1129		4		136
1116		5		142
1105		6		151
1099		7		163
1096		8		168
1088		9		181
1074		10		185
1069		11		188
1068		12		423
1065		13		495
1060		15		52381
1055		18		59410
1054		16		65428
1053		16		87494

Optimization completed
----------------------
number of nodes     : 24
number of edges     : 52
number of demands   : 552
first solution time : 3
optimization time   : 180771
initial max maxLinkLoad    : 1188
final max maxLinkLoad      : 1053
number of tunnels   : 16
pre-optimization max link utilization 1.18901772954
post-optimization max link utilization 1.0543248478600002
2 demands over 552 (0.36231884057971014%) have a different segment routing path between pre-optimization and post-optimization

Optimization time (in seconds): 180.796413866